The project consists of 5 Towers each comprising 25 Floors and a Roof with 3 Parking Buildings, for a total of PT area of 150,000m2. Each week there were 3 pours of concrete being poured, and ESF provided full support to the main contractor to achieve the aimed cycle of slabs.
Main Contractor: Bu Haleeba Contracting LLC
Consultant : Archgroup
Total PT Area: 150,000m2
No. of PT slabs: 130
Location: Dubai Silicon Oasis, Dubai
Completion Date: November 2016